A change order is the formal record of a change to contracted scope, cost or time. It may arise from an owner request, concealed condition, design revision or field coordination issue. The goal is not to eliminate every change, but to prevent unclear work from becoming an unclear obligation.

Start with entitlement

Before debating price, determine why the work is outside the original contract. Compare the proposal with drawings, specifications, clarifications, allowances and prior decisions. Separate true added scope from work already required or from correction of defective work.

Review quantity, rate and schedule

A useful proposal shows labor, material, equipment, subcontractor cost, markup and schedule effect. The representative checks quantities and assumptions, asks about alternatives and identifies credits for deleted work. Time extensions should connect to the critical sequence rather than appear as a generic allowance.

Approve before proceeding

Except for emergencies, changed work should not begin without documented direction and an agreed process. Maintain a log of requests, proposals, approvals and pending exposure. Forecast likely changes before they are executed so the owner sees the expected final cost, not only today’s committed total.

Put the guidance into a real project

Use this guidance to define authority before the project accelerates. List who can direct work, approve cost, accept schedule changes and sign off on design decisions. Then establish a single log for open questions, owner decisions, potential changes and closeout items. The owner’s representative should make information easier to act on—not create a parallel chain of command. Clear contracts, concise reports and timely recommendations allow the architect and contractor to perform their roles while the owner retains visibility and control.

A practical review checklist

  • Reason and contractual basis
  • Detailed scope and quantities
  • Labor, material, equipment and markup
  • Credits and alternative solutions
  • Schedule effect and written authorization

Frequently asked questions

Are all change orders avoidable?

No. Concealed conditions and legitimate owner changes can be unavoidable.

Can work proceed before price is final?

Sometimes under written time-and-material or not-to-exceed authorization, with strict documentation.

What is a change-order log?

A live record of potential, proposed, approved and rejected changes and their budget effect.